Providing the latest development news and construction progress.

   

Latest Oceana News




   

Latest Oceana News - August 3, 2016







   

Latest Oceana News - July 24, 2016




   

Latest Oceana News - September 2015




What's happening?

The rainy season is most definitely upon us as "Tropical Storm Vamco" comes to Phuket.
With some heavy downpours and generally stormy weather to deal with, work on site has been a little disrupted this month.
However construction work continues to progress, and here's whats been happening:

Construction update:

August & September:

      -Piling Tower B complete.
      -Retaining wall for car park area Tower A/B complete.
      -Cut piling Tower A complete.
      -Prepare footings Tower A / B.
      -Retaining wall work Tower B.

October:

      -Pour concrete for footing Tower A.
      -Start structure 1st floor.
      -Start retaining wall commercial building.


We look forward to adding more construction photos to our website in the coming weeks so please feel free to visit from time to time.

For more construction photos please visit our construction progress.




   

Latest Oceana News - July 2015

What's happening?

Construction update:

July:

      -Tower A piling complete.
      -Drilling for ground water supply.

August:

      -Starting piling work Tower B
      -Start work on retaining wall for car park area Tower A/B.
      -Testing piling for Tower A.


We look forward to adding more construction photos to our website in the coming weeks so please feel free to visit from time to time.

For more construction photos please visit our construction progress.




   

Latest Oceana News - June 2015

What's happening?

Construction update:

- Piling work for Tower A begins.

We look forward to adding more construction photos to our website in the coming weeks so please feel free to visit from time to time.

For more construction photos please visit our construction progress.